Neighbor to Neighbor: Updates from Our Ohio Falls Generating Station

Ohio Falls Hydro Station

Ohio Falls Generating Station

Marty Downs at the Ohio Falls Hydro StationLouisville’s location on the Ohio River allows the opportunity for LG&E to safely harness the natural energy of the river to create electricity. Ohio Falls Hydro Station was built in the mid 1920’s and was commissioned in 1927.

The station is uniquely located within the McAlpine Locks and Dam Navigational Project and the Falls of the Ohio Natural Wildlife Conservation Area. The Army Corps of Engineers operates the dam and spill gates at the Falls to help control and monitor the flow of the river for navigation.

Water first flows through a set of trash bars, which prevent large pieces of debris, such as trees, stumps and trash, from going through the units and causing damage. After passing through the trash bars, the water flows through the turbine, whose blades rotate a shaft connected to the generator, which also rotates with the turbine. When the generator rotates, electricity is produced. The water then flows out of the plant unaltered and continues down river.

During the plant’s first years of operation, the amount of electricity generated by the Ohio Falls Station provided most of the power needed to serve the city of Louisville. The relatively small capacity of the hydroelectric plant, however, quickly became insufficient to meet the needs of the growing city. More than 80 years later, this cost-effective, environmentally friendly source of power continues to operate.

-Go to top-


Ohio Falls Project Updates

Upgrades at the Ohio Falls Station In addition to major new investments in state-of-the-art power generation and environmental controls, the company is increasing its non-emitting generation capacity to enhance the diversity of its generation portfolio and minimize its effect on the environment.

In 2005, LG&E renewed its license to operate the Ohio Falls Hydroelectric Station. A rehabilitation project is currently underway to update and refurbish the eight existing turbine/generator units over the next several years.

The project consists of a three-phase upgrade, two of which are already completed. When the entire work is finished in 2015, generation will increase from 80 to 102 megawatts, a 27-percent rise.

Phase I: Design, procurement and installation of equipment for automating and remote-operation of all units. Completed in 2002.

Phase II: Design, procurement and installation of equipment to upgrade trash-removal systems and flow model testing. Also, installation of trash-rack cleaning machine, sluice gate and trash racks. Completed in 2004-’05.

Phase III: Complete rehab of the 8 units, which is scheduled to be finished in 2015. Work includes: new runner, rewinding the generator, stator restack, converting rotating exciter to static excitation and refurbishment of wicket gates.

-Go to top-


In Your Community
Boy Scouts, LG&E Employees Complete Pedestrain FootpathBoy Scouts, LG&E Employees Complete Pedestrian Footpath near Ohio Falls

Pedestrians on Shippingport Island in Louisville now have easier access to fishing on the riverbank thanks to the hard work of Boy Scouts from Troop #167 and LG&E. The Boy Scouts — with help from employees at LG&E’s Ohio Falls Hydroelectric Station — worked to install a pedestrian footpath on the island to help one of the troop’s members achieve the coveted rank of Eagle Scout.

Employees from the company’s Cane Run and Mill Creek generating stations helped deliver railroad ties from the plants that will be used as a border for the footpath. Ohio Falls’ employees provided on-site support, and Nelson Tree Service donated two truckloads of mulch to surface the trail. The Army Corps. of Engineers, which owns the property, granted access to the site.

-Go to top-


Ohio Falls Generating Station Quick Facts

Net Output Capacity: 80 megawatts

Original Startup Date: 1927

Fuel: Hydro

Number of Units in Service: 8